This 0.5-mile resurfacing project in the Town of Beloit was funded through the State Transportation Program-Urban (STP-Urban). The project resurfaced the four-lane section of CTH Q from CTH D to the Newark Road Bridge over the Rock River, and also added an off-road multi-use path along the south side of CTH Q. This is part of a larger initiative by Rock County with a future project that will extend the multi-use path along the east side of CTH D from CTH Q to Big Hill Park. The design of the multi-use path involved complex drainage design/considerations through the Town of Beloit Fire Station. A combination of a mountable curb and a series of inlets and storm sewers was required to maintain drainage from CTH Q within the existing right-of-way after installation of the path.
Multiple alternatives were developed for the section east of the Fire Station, as the county right-of-way becomes very wide, allowing the path to traverse an existing wooded section